50 MW Melowind wind farm is located in the department of Cerro Largo. Its production level is over 200 million kilowatt hours (kWh) per year.
After a difficult selection process, Ingener was selected for designing and implementing the electro-mechanical assembly and the civil works of the 31.5/150 kV step-up substation, the UTE 150kV utility substation and the 31.5kV internal network.
The client also awarded Ingener the construction of 12 foundation bases for Nordex 2.5 MW wind turbines.
MELOWIND WIND FARM – 50 MW
                            Cerro Largo, Uruguay, 2014/2015                        
                        
                                                    Areas of expertise:
                        
                           RenewableWind Energy                        
                    Electaparc S.A
 
        	    	