VILLALONGA WIND FARM – 50 MW

Contract amount: USD 2.500.000
Villalonga, province of Buenos Aires, 2017/2018
Areas of expertise: RenewableWind Energy

Genneia. Subcontract from Milicic

VILLALONGA WIND FARM – 50 MW

Genneia. Subcontract from Milicic Ingener built the electrical infrastructure of the wind farm owned by Genneia group.
Milicic company, in consortium with ABB, run the electrical and civil BOP of 50 MW Villalonga wind farm, located near the city of Villalonga, province of Buenos Aires. The construction consortium subcontracted to Ingener the complete electro-mechanical assembly of the 132/33 kV substation; opening of the high voltage overhead line and connection to the 132 kV transmission network; and stringing and connection of the 33 kV internal network.