Flores, Uruguay — 2016/2017
Client: GAMESA
The wind farm, located in the department of Flores, comprises 35 wind turbines of 2 MW each, generating 300 GWh per year, with a capacity of 70 MW.
As part of this project, Gamesa entrusted Ingener with:
-Detailed engineering.
-Complete installation of the MV collection network.
-Installation and termination of the wind turbine switchgear.
-EPC construction of the step-up substation, the connection and metering point (PCyM) and the connection to the 150 kV transmission grid.