A.N.N.P. 150 kV Interconnection

Montevideo, Uruguay · 2022/In progress

Montevideo, Uruguay — 2022/In progress

The project involves laying two new 150 kV underground cable circuits to interconnect the Montevideo A (MVA), Montevideo Norte (NOR) and Montevideo P (MVP) substations. These works will reinforce the power transmission infrastructure in Montevideo, increasing the system’s reliability and operational flexibility.