Santa Cruz, Argentina — 2019/2022
Client: YPF LUZ. Subcontract for GE GRID
As part of the Cañadón León wind farm project developed by YPF Luz, the 132/500 kV Santa Cruz Norte transformer substation, located near the city of Pico Truncado in the province of Santa Cruz, is being expanded.
The works are carried out by GE Grid under an EPC contract, which subcontracted Ingener for the following substation expansion tasks:
-Detailed civil engineering.
-Complete civil works.
-Electromechanical installation.
-Construction of 132 kV and 500 kV bays.
-Installation of a new 132/500 kV autotransformer bank.