Villalonga Wind Farm – 50 MW

Villalonga, Buenos Aires Province · 2017/2018

Villalonga, Buenos Aires Province — 2017/2018

Client: Genneia. Subcontract for Milicic

Ingener built the electrical infrastructure of the wind farm in Villalonga, Buenos Aires Province, Argentina, owned by Grupo Genneia.

 

Milicic, in a consortium with ABB, executed the electrical and civil BOP for this 50 MW wind farm.

 

The construction consortium hired Ingener to lead the complete electromechanical installation of the 33/132 kV transformer substation, as well as the line loop-in and connection to the 132 kV transmission grid, and the laying and connection of the wind farm’s 33 kV internal collection network.